MCS 041 Operating System Solution
Dear Friends here we post the available solution to the assignments if you have any doubt about any question please comment it. Question 1: (a) Assume you have the following jobs to execute with one processor Process Burst Time Arrival Time P1 75 0 P2 40 10 P3 25 10 P4 20 80 P5 45 85 Support a system uses RR scheduling with a quantum of 15. a) Create a Gantt chart illustrating the execution of these processes. b) What is turn around time for process P3. c) What is the average wait time for the processes?